Sec.8-119jj-28. Terms and conditions  


Latest version.
  • (a) A developers' fee may be established at up to 10% of the total development cost, less the cost of land, or $100,000, whichever is less.

    (b) The fee schedule shall be determined as follows:

    Percent of Fee

    Key Event

    10%

    Preliminary Application

    15%

    Final Application

    25%

    Construction Start

    50%

    Construction Completion

    (c) Developer's fees are earned based on the schedule established for completing key events in the development process, as approved by the Commissioner.

    (d) Developers shall only earn a fee for those key events that are completed according to the established schedule. Developers may not be entitled to earn a fee for key events completed after the established schedule. Developers shall earn, but not receive, any fee, until completion of the housing development.

(Effective December 27, 1990)