  • (a) Supervisory Personnel.

    The certificate holder, or facility owner or operator, shall submit to the Council contact information for the personnel of the contractor assigned to the project.

    (b) Notice.

    (1) The certificate holder, or facility owner or operator, shall provide the Council, in writing, with a minimum of two weeks advance notice of the beginning of:

    (A) clearing and access work, and

    (B) construction of the tower and associated equipment.

    (2) The certificate holder, or facility owner or operator, shall provide the Council with advance written notice whenever a significant modification of the approved D&M plan is necessary including, but not limited to, a change in the location of the tower, associated equipment, guy wires, or access road. The Council, or its designee shall promptly review the changes, and the Council shall approve, modify, or disapprove the changes in accordance with subsection (d) of Section 16-50j-75 of the Regulations of Connecticut State Agencies.

    (3) The certificate holder, or facility owner or operator, shall provide the Council with a monthly construction progress report, or a construction progress report at time intervals determined by the Council, indicating changes and deviations from the approved D&M plan. The Council may approve the changes and deviations or request corrections or mitigating measures.

    (4) The certificate holder, or facility owner or operator, shall provide the Council with written notice of completion of construction and site rehabilitation.

    (c) Final report.

    The certificate holder, or facility owner or operator, shall provide the Council with a final report not later than 180 days after completion of all site construction and site rehabilitation. This final report shall identify:

    (1) all agreements with abutters or other property owners regarding special maintenance precautions;

    (2) significant modifications of the D&M plan that were required because of the property rights of underlying and adjoining owners or for other reasons;

    (3) the location of construction materials which have been left in place in the form of culverts, erosion control structures along watercourses and steep slopes, and corduroy roads in regulated wetlands;

    (4) the location of special areas where special planting and reseeding have been done; and

    (5) agreements between the certificate holder and public agencies authorizing public recreational use of the site to the extent of the certificate holder's property rights thereto.

    (d) The final report shall include the actual construction cost of the tower and associated equipment, including, but not limited to, the following costs:

    (1) construction of the tower and associated equipment;

    (2) site rehabilitation; and

    (3) property acquisition for site or access to site.

    (e) Protective Order.

    The certificate holder, or facility owner or operator, may file a motion for a protective order pertaining to commercial or financial information related to the site or access to the site.

(Effective May 28, 1985; Amended September 7, 2012)