Regulations of Connecticut State Agencies (Last Updated: June 14,2023) |
Title16 Public Service Companies |
SubTitle16-262m-1_16-262m-9. Certificates of Convenience and Necessity for Small Water Companies |
Sec.16-262m-7. Components of the application under phase II
-
Engineering data certified by a professional engineer registered in the State of Connecticut as follows:
(a) Plans and specifications for the project must include but not be limited to: transfer pumps, well pumps and pump curves, hydropneumatic tanks, treatment facilities, distribution system layout, atmospheric storage facilities, metering (each source and customer), location of sample taps, on-site standby power, presence of emergency alarms, location of pressure gauges, location of gate valves and blow-offs, water level gauges on storage tank, fire protection (if necessary), and disinfection procedures;
(b) A hydraulic gradient of the proposed system;
(c) A detail of a typical service line, service connection, thrust block installation, hydrant installation, cross-section of trench containing pipe, and a meter installation;
(d) A plan and profile drawing of the water main and all other underground utilities (sewer, gas, electric, telephone or cable television);
(e) Name, address, telephone number and title of proposed operator with day-to-day responsibility for system.
(Effective September 25, 1987)