Sec.16-11-138. Petition for commission approval—communication lines  


Latest version.
  • Where communication and electric lines are both aerial or both underground, no communication line shall be extended so as to cross, conflict or establish joint use with an electric line over twenty thousand nominal volts to ground without prior commission approval. A petition for such approval shall be submitted to the commission and said petition shall state the following: (1) The purpose for which the line is to be built, (2) the towns in which it is located; (3) sufficient information to identify the electric line involved, (4) special features employed at points of crossing; (5) the names of all other utilities and municipalities whose circuits are involved in the proposed crossing, conflict or joint use.