Sec.16-333-14. Petition and supporting data  


Latest version.
  • No CATV cable or extensions shall be constructed without prior commission approval. Petition for such approval shall be submitted to the commission at least thirty days prior to the proposed date of construction and shall furnish the following information:

    (a) The location of the proposed construction;

    (b) the names of all public service companies and municipalities involved;

    (c) a map showing routes of the television cable;

    (d) the location of amplifiers, power supplies, television tower and all other major components of the television cable system.

(Effective November 25, 1969)